infrastructure · pivotal

IFA interconnector fire (Sellindge converter station)

15 September 2021 → 1 October 2023

Fire at Sellindge converter station in Kent halved IFA capacity from 2,000 MW to 1,000 MW. Full restoration October 2023, a 25-month outage that compounded the 2021-22 energy price crisis.

Affected fuels: imports, imports_fr

Countries: GB, FR

Sources

  1. www.gov.uk(accessed 2026-04-26)
  2. www.theguardian.com(accessed 2026-04-26)
  3. www.energyvoice.com(accessed 2026-04-26)

← All UK energy events