EDF announces Hinkley Point C cost and timeline revision
23 January 2024
EDF revised Hinkley Point C cost to £31-34bn (2015 prices) — up from a previous £26bn cap — and pushed first-power scenarios to 2029-2031, citing Covid, Brexit, civil-construction inflation, and labour/material shortages.
Affected fuels: nuclear
Countries: GB
Sources
- www.world-nuclear-news.org(accessed 2026-04-26)
- www.newcivilengineer.com(accessed 2026-04-26)