Dogger Bank A delivers first power
7 October 2023 → 7 October 2023
Dogger Bank A — first phase of the world's largest offshore wind project — delivered first power at 20:37 BST on 7 Oct 2023 from a GE Haliade-X 14 MW, the first Haliade-X to generate at scale. 1.2 GW phase A targets full commissioning 2025; total A+B+C 3.6 GW.
Affected fuels: wind_offshore
Countries: GB, NO