Small Modular Reactors: Britain's £2.5 Billion Gamble on Nuclear Revival
The UK has selected Rolls-Royce to build its first SMRs at Wylfa, committing £2.5bn to a technology with no commercial track record. Is this the solution to Britain's energy crisis, or a repeat of nuclear's troubled history?
In June 2025, the UK government selected Rolls-Royce SMR as its preferred partner to build Britain’s first small modular reactors. In November, it announced Wylfa in North Wales as the site for three initial reactors.
The government is committing over £2.5 billion to this programme. Energy Secretary Ed Miliband called it the start of “a golden age of nuclear.” Chancellor Rachel Reeves said it puts the UK “at the lead in the technologies of tomorrow.”
The stakes are high. Britain imports 40% of its energy at a cost of £24.3 billion annually. Nuclear output has collapsed from 100 TWh to 41 TWh over two decades. If SMRs work as promised, they could reverse this decline, providing reliable baseload power with a 258× smaller land footprint than wind.
If they don’t, Britain will have repeated the mistakes of Hinkley Point C on a smaller scale, multiple times over.
What Is an SMR?
Small modular reactors are nuclear power plants designed to be smaller, simpler, and faster to build than conventional reactors. The “modular” part is key: instead of constructing a bespoke power station on site, components are manufactured in factories and assembled like large industrial equipment.
Rolls-Royce SMR specifications:
- Power output: 470 MWe (megawatts electrical)
- Thermal capacity: 1,358 MWt
- Technology: Pressurised water reactor (PWR), the same proven technology used in most of the world’s nuclear fleet
- Land footprint: Approximately 4 hectares (10 acres) total site, with a 1.5-acre reactor building footprint
- Design life: 60 years
For context, Hinkley Point C’s two reactors will produce 3.26 GW combined. You would need seven Rolls-Royce SMRs to match that output, but each SMR could be built faster and at a different location.
The theoretical advantages are compelling:
- Factory manufacturing reduces on-site construction complexity
- Standardised design means learning from each build
- Smaller units allow deployment at more sites
- Shorter construction times reduce financing costs
- Modular expansion lets capacity grow with demand
The question is whether these advantages survive contact with reality.
The UK’s SMR Programme: Timeline and Funding
The path to the November 2025 announcement has been long and uncertain.
Key milestones:
| Date | Event |
|---|---|
| November 2021 | Government provides £210 million to Rolls-Royce SMR for design development |
| July 2023 | Great British Nuclear launches SMR competition with six vendors |
| January 2024 | Civil Nuclear Roadmap published, targeting 24 GW nuclear capacity by 2050 |
| March 2024 | Great British Nuclear acquires Wylfa and Oldbury sites from Hitachi for £160 million |
| April 2022 | Rolls-Royce SMR enters Generic Design Assessment with ONR |
| July 2024 | Rolls-Royce SMR progresses to Step 3 (final phase) of GDA |
| June 2025 | Rolls-Royce selected as preferred technology partner |
| November 2025 | Wylfa announced as first SMR site |
Funding committed:
- £210 million: Initial government grant for design development (2021)
- £195 million: Private investment from Rolls-Royce Group, BNF Resources UK Limited, and Exelon Generation Limited
- £160 million: Site acquisition (Wylfa and Oldbury)
- £2.5 billion+: Programme commitment in current Spending Review period
Projected timeline:
- August 2026: GDA completion expected
- 2026: Site activity begins at Wylfa
- Mid-2030s: First power to grid
- 2030s: All three initial SMRs operational
This timeline is ambitious. The Generic Design Assessment alone takes 53 months. Site licensing, construction permits, and actual building will take years more. The “mid-2030s” target for first power is a decade away.
The Cost Question
Rolls-Royce’s cost projections have evolved:
- Initial estimate: £1.8 billion per 470 MW unit once in full production
- First-of-a-kind cost: £2.2 billion per unit
- Learning curve target: £1.8 billion by the fifth unit built
To put these numbers in context:
Cost per GW of capacity:
- Rolls-Royce SMR (target): £3.8 billion/GW
- Hinkley Point C (current estimate): £10.7-14.7 billion/GW (based on £35-48 billion for 3.26 GW)
- Offshore wind: £1.5-2.5 billion/GW (but requires backup capacity)
On paper, SMRs look competitive. But these are projections, not proven costs.
The Hinkley Point C warning:
Britain’s only nuclear plant currently under construction provides a cautionary tale. When approved in 2016, Hinkley Point C was expected to cost £18 billion and begin operations in 2025.
Current estimates: £35-48 billion, with first power between 2029 and 2031.
That is a 94-167% cost overrun and a 4-6 year delay, and it isn’t finished yet.
EDF’s site managing director cited “civil construction slower than we hoped and faced inflation, labour and material shortages, on top of Covid and Brexit disruption”.
SMR proponents argue their technology avoids these problems through factory manufacturing and standardised design. But no Rolls-Royce SMR has been built anywhere. The claimed efficiencies are theoretical.
International Context: No Commercial SMR Fleet Exists
The UK is betting on technology that has not been commercially deployed anywhere in the world.
Global SMR status (November 2025):
| Country | Project | Status |
|---|---|---|
| USA | NuScale VOYGR (Idaho) | Cancelled November 2023 - costs rose from $3.6bn to $9.3bn |
| Russia | Akademik Lomonosov | Operational (floating, 70 MW total) - significant delays and cost overruns |
| China | HTR-PM | Operational (210 MW) - 7+ years late, costs undisclosed |
| Canada | Multiple projects | In development, no construction started |
| Romania | NuScale project | FEED stage (planning only) |
The only operational SMRs are in Russia and China, both with government backing that obscures true costs. Both projects experienced significant delays.
The NuScale cancellation is particularly relevant. NuScale was the first SMR design to receive US Nuclear Regulatory Commission certification. Its Utah project was the most advanced Western SMR development. It was cancelled because costs more than doubled from original estimates, from $3.6 billion to $9.3 billion.
NuScale was also a finalist in the UK’s SMR competition before being eliminated in September 2024.
This does not mean Rolls-Royce SMR will fail. But it means there is no proven cost or timeline data for commercial SMR deployment anywhere. Every projection is theoretical.
Why Wylfa?
The choice of Wylfa in Anglesey, North Wales, is significant.
Site history:
- Wylfa housed two Magnox reactors from 1971 until 2015
- Wylfa Newydd, a proposed large reactor project, was abandoned by Hitachi in 2020 after costs escalated
- Great British Nuclear acquired the site in March 2024
Advantages:
- Existing grid connections
- Nuclear-experienced local workforce
- Community familiar with nuclear operations
- Coastal location for water cooling
- Previous environmental assessments completed
Capacity potential: The government says Wylfa could eventually host up to eight SMRs, producing approximately 3.76 GW, more than Hinkley Point C.
The Oldbury site in Gloucestershire remains available for future expansion, potentially for “privately-led projects.”
Jobs and Supply Chain
The government projects significant employment benefits:
- 3,000 skilled jobs at peak construction
- 70% supply chain targeted to be British-built
- 40,000 jobs across the supply chain once a fleet is operational (Rolls-Royce projection)
Current UK nuclear employment:
- 87,000 direct jobs in the civil nuclear supply chain
- 256,000 total jobs supported by the sector
- Average GVA per employee: £92,000, nearly twice the UK average
Supply chain challenges:
The UK’s nuclear supply chain has atrophied during two decades without new construction. Industry reports note significant skills gaps, particularly in:
- Nuclear welding and fabrication
- Reactor component manufacturing
- Project management for nuclear-grade construction
The government’s Nuclear Skills Taskforce is attempting to address this, but rebuilding expertise takes years. Meanwhile, Hinkley Point C has relied heavily on imported expertise and components.
SMR proponents argue factory manufacturing could be done domestically, but the factories don’t exist yet. Rolls-Royce SMR partnered with the University of Sheffield in 2024 to create manufacturing and testing facilities, but these are years from production scale.
The Regulatory Hurdle
Before any SMR can be built, it must complete the Generic Design Assessment (GDA), a rigorous safety review by the Office for Nuclear Regulation (ONR) and Environment Agency.
Rolls-Royce SMR GDA timeline:
- Step 1 (April 2022 - March 2023): Initial assessment, 12 months
- Step 2 (April 2023 - July 2024): Fundamental assessment, 16 months
- Step 3 (July 2024 - August 2026): Detailed assessment, ~25 months expected
Total duration: 53 months (4.4 years)
No other SMR design is as far advanced in UK regulatory approval. Holtec, GE-Hitachi, and Westinghouse (the other competition finalists) would need to start their own GDA processes from scratch if they wished to build in the UK.
This is both a regulatory advantage for Rolls-Royce and a vulnerability for the UK programme. If Rolls-Royce encounters problems, there is no backup option with comparable regulatory progress.
The Case For SMRs
Despite uncertainties, the case for SMRs is substantial:
1. Energy security
Britain’s 40% energy import dependency leaves us vulnerable to price shocks and geopolitical disruption. Nuclear provides domestic baseload power that doesn’t depend on imported gas or Russian uranium (UK uses enriched uranium from domestic and allied sources).
2. Grid stability
Unlike wind and solar, nuclear provides dispatchable power 24/7. As Britain adds more intermittent renewables, stable baseload becomes more valuable. SMRs could complement renewables by filling gaps when wind doesn’t blow.
3. Land efficiency
A single SMR produces 470 MW from a 10-acre site. Equivalent wind capacity would require approximately 45,000 acres, with lower capacity factor. For a crowded island, land efficiency matters.
4. Decarbonisation
Nuclear produces approximately 5-12 gCO2/kWh lifecycle emissions, comparable to wind and lower than solar (when manufacturing is included). It generates zero emissions during operation.
5. Industrial strategy
A successful SMR programme could establish UK leadership in a potentially significant export market. Countries seeking to decarbonise will need nuclear options, and British-designed SMRs could compete globally.
The Case Against (Or at Least for Caution)
The risks are equally substantial:
1. No commercial track record
Not a single commercial SMR fleet operates anywhere in the world. The UK is betting billions on unproven technology. Every cost and timeline projection is theoretical.
2. Nuclear’s troubled history
British nuclear construction has a poor record. The AGR programme in the 1970s-80s was, in the words of the Central Electricity Generating Board’s former head, “a catastrophe we must not repeat”. Dungeness B was 12 years late. Most AGRs had huge cost overruns.
Hinkley Point C is following the same pattern. There is no evidence that lessons have been learned.
3. Cost escalation risk
NuScale’s cancellation after costs doubled is a warning. First-of-a-kind nuclear projects routinely exceed budgets. The £2.2 billion per unit estimate could easily become £4 billion.
4. Timeline risk
“Mid-2030s” for first power is already a decade away. If GDA takes longer than expected, or construction hits problems, the timeline could slip further. Britain’s energy crisis is now, not in 2035.
5. Opportunity cost
£2.5 billion+ invested in SMRs is £2.5 billion not invested in alternatives: offshore wind, grid storage, demand flexibility, or interconnectors. If SMRs fail or are significantly delayed, that money is lost.
What Success Would Look Like
For SMRs to justify the investment, they need to achieve:
- GDA completion by August 2026 as scheduled
- First power by mid-2030s as targeted
- Costs at or below £2.2 billion for the first unit
- Learning curve realised: subsequent units built faster and cheaper
- Export orders: demonstrating commercial viability to international buyers
The government should publish transparent progress reports against these metrics. Taxpayers are entitled to know whether their investment is delivering.
Conclusion: A Calculated Risk
Britain’s SMR programme is neither obviously right nor obviously wrong. It is a calculated risk on technology that could help solve our energy security crisis, or could repeat the expensive failures of past nuclear projects.
The arguments for attempting this are strong:
- Nuclear is the only proven low-carbon baseload technology
- Britain’s energy import dependency is a strategic vulnerability
- SMRs could complement renewables in a way large reactors cannot
- The UK has site, skills, and regulatory infrastructure to attempt this
The arguments for caution are equally strong:
- No commercial SMR exists anywhere
- Every cost and timeline estimate is theoretical
- British nuclear construction has a troubled history
- The money could be spent on proven alternatives
What would be inexcusable is proceeding without transparency. The government has committed £2.5 billion of public money. It should publish quarterly progress reports, cost updates, and honest assessments of problems encountered.
If Rolls-Royce SMR works as promised, this could be the beginning of Britain’s nuclear renaissance. If it doesn’t, we need to know early enough to change course.
The £2.5 billion gamble is underway. Now we wait to see whether the bet pays off.
Key Sources
- Rolls-Royce SMR Selected - GOV.UK (June 2025)
- Wylfa Site Selection - World Nuclear News (November 2025)
- GDA Process - Office for Nuclear Regulation
- Civil Nuclear Roadmap - GOV.UK (January 2024)
- Site Acquisition - GOV.UK (March 2024)
- Hinkley Point C Cost Update - World Nuclear News (January 2024)
- NuScale Cancellation - World Nuclear News (November 2023)
- UK Nuclear Employment - Nuclear Industry Association (2024)